Days River Road/Stream Crossing Replacement Site DRT 01

Grant: # 1898

Grant Amount: $42,901.84

Board Decision Year: 2020

Delta County Road Commission (Escanaba)

Roseman, Nancy ([email protected]) (906) 786-3200 Ext. 14

2020 Habitat Protection and Restoration - Habitat protection and restoration

Project Summary

The purpose of this project is the replacement of the existing 24" diameter culverts with 87" X 63" Aluminized Steel Pipe Arch Culverts at 2 locations on Days River Road. The proposed structures will provide natural stream beds, reduce velocities and result in improved passage for aquatic organisms and a reduction in sediment. An additional culvert under an abandoned trail will be removed contingent upon permission by the Property Owner (State of Michigan).